Virginia Beach's Laskin Road widening project, delayed by soil and utility issues, nears $150M completion.
The Laskin Road widening project in Virginia Beach, started in 2017, is nearly complete after facing delays due to soil conditions and utility conflicts.
Initially projected for 2023, the $150 million project, with $42.7 million from the city, saw the contractor, Allan Myers, Inc., finish work on the west side by November with a $1.5 million incentive.
Remaining tasks include bridge replacement, roadway work, lighting, and landscaping, with completion expected by spring 2025.
3 Articles
El proyecto de ampliación Laskin Road de Virginia Beach, retrasado por problemas de suelo y servicios públicos, se acerca a la finalización de $150M.