flag The first train delivered construction materials to the Sizewell C nuclear site, marking a key milestone in the project’s development.

flag The first engineering train arrived at the Sizewell C nuclear plant site in Suffolk on February 23, 2026, marking a key construction milestone. flag The train delivered aggregate via the upgraded Sizewell branch line, which has been modernized with new track, signaling, and improved crossings. flag The rail delivery reduces the need for up to 50 heavy goods vehicles per train, supporting plans for up to four freight trains daily. flag The project, led by Balfour Beatty Rail, aims to minimize road disruption and carbon emissions. flag Once complete, temporary rail lines will be removed and the land restored. flag The branch line has not carried passenger service since 1966.