flag The British Museum awarded Dalkia a £33M contract to build a low-carbon energy center, replacing gas boilers with electric heat pumps, cutting 1,700 tonnes of carbon annually, with work starting in 2024 and completion expected in 2029.

flag The British Museum has awarded Dalkia a £33 million contract to build a low-carbon energy centre, replacing gas-fired boilers with electric systems including a 5.1MW air-source and 7MW water-source heat pump, plus a 900kW backup boiler. flag The project, part of a broader sustainability effort, aims to cut carbon emissions by 1,700 tonnes annually, improve energy resilience, and support the museum’s net-zero goal. flag Construction began in 2024, with completion expected in 2029.