The Crownview Apartments project in Wollongong remains under a third extension of its Stop Work Order due to ongoing unauthorized construction, with limited safety work allowed and buyers refunded.
The Crownview Apartments project near Wollongong Hospital has been under a third extension of its Stop Work Order, issued by NSW Building Commission due to ongoing unauthorized construction.
The order, first imposed in February 2024, was renewed in 2025 and again in February 2026 after inspections found work continued despite prohibitions.
The site remains under a Prohibition Order and a Building Works Rectification Order.
The extension allows limited safety-related work, including fire system upgrades, while the developer arranges for a qualified builder to complete remedial work.
All buyers have reportedly had deposits refunded following intervention by former Building Commissioner David Chandler.
A complex engineering solution is expected to ensure structural safety, but the project’s future remains uncertain as officials continue coordinating on remediation plans.