The Hombre Muerto West lithium project in Argentina is 85% complete, with production set for early 2026.
The Hombre Muerto West (HMW) Phase 1 lithium project in Argentina is 85% complete, with the nanofiltration plant delivered and on-site assembly underway.
Evaporation ponds are finished, enabling early 2026 production of processed brine and lithium chloride concentrate.
The project, which has accumulated about 9,500 tonnes of lithium brine, aims for 5,200 tonnes per year of lithium carbonate equivalent after a January 2026 capital raise.
Key milestones include system commissioning and full operational readiness.