Orvana Minerals begins trial processing at Bolivia’s Don Mario mine, with initial doré production expected by late February 2026.
Orvana Minerals reports progress at its Don Mario mine in Bolivia, with trial processing of sulfide ore underway and initial doré production expected by late February 2026.
Copper processing circuits are under construction, with full commissioning targeted for early Q3 FY2026.
Oxide stockpile processing will follow, ramping up through Q3 and aiming for full capacity by Q4.
Initial production rates and recovery efficiencies will be below long-term targets due to ongoing optimization.
Guidance is based on pilot testing and metallurgical data, remains preliminary, and may be updated as operations progress.