The BorWin6 offshore project completed loading its 5,461-ton foundation in UAE, a key step for Germany’s North Sea wind grid connection.
The BorWin6 offshore HVDC project has successfully completed the loadout of its 5,461-ton jacket foundation in Jebel Ali, UAE, marking a key milestone.
The structure, part of a 980-megawatt grid connection for Germany’s North Sea wind energy, will be transported to Europe.
Mammoet managed the operation using 216 SPMTs and winch systems under an EPCI contract led by McDermott International for TenneT.
Next, the 17,000-ton topside will be lifted and weighed using Mammoet’s Mega Jack 5200 system before skidded loadout and sailaway later in 2026.