flag Fargo approved a $25M interchange project on I-29 and 64th Ave S, with construction starting in 2028 and finishing by 2029.

The Fargo City Commission approved a $25 million partial cloverleaf interchange at 64th Avenue South and I-29 on January 20, 2026, with construction set to begin in spring 2028 and finish by fall 2029. The chosen design includes a traffic signal on the west ramp and a roundabout on the east ramp, along with roadway widenings, turn lanes, bridge improvements, and shared path upgrades. The project, funded by $21.25 million in federal Interstate Maintenance funds, must be completed as designated or the money will revert to the state. Officials emphasized the need to balance regional mobility with neighborhood safety, noting that both ramps should be built or neither.