A 2025 fire damaged Dublin's George's Dock Bridge, leading to a rapid rebuild reopened in November.
A fire in August 2025 severely damaged Dublin’s George’s Dock Bridge, warping steel, cracking concrete, and buckling rails, prompting engineers to conclude rebuilding was more cost-effective than repair.
The National Transport Authority constructed a new bridge using off-site fabrication, reopening it in late November 2025—just over three months after the fire—just in time for the Christmas season.
The cause remains unconfirmed, though a gas pipeline rupture is suspected.
The €7 million project was funded by the NTA and Transdev, with both agencies pursuing insurance claims.