Construction on Wollongong's Mount Ousley interchange paused for Christmas, resuming Jan. 5, 2026.
Construction on the Mount Ousley interchange in Wollongong has paused for the Christmas break, resuming January 5, 2026.
The project, one-third complete after a year of progress, has seen 357,000 person-hours invested, with work on bridge piers, retaining walls, and a new heavy vehicle safety ramp.
A shared pedestrian and cycle bridge was reinstated following public feedback, adding $12 million to the cost.
Four two-day closures in early 2026 will widen and raise Mount Ousley Road, reducing night work by nine months.
Upcoming milestones include pouring the concrete deck for the Mount Ousley Road bridge over the heavy vehicle bypass, opening the new safety ramp, and expanding southbound access to University Avenue.
Transport for NSW thanked the community for its patience.