flag Revolve Renewable Power Corp. received Mexico’s final permit for its 130 MW El 24 Wind Project, enabling grid connection and advancing it to ready-to-build status.

flag Revolve Renewable Power Corp. has secured a final Generation Permit from Mexico’s CNE for its 130 MW El 24 Wind Project in Tamaulipas, approved December 19, 2025, one of only five wind projects nationwide to receive such approval under an accelerated process. flag The permit allows the project to generate electricity and connect to the national grid, advancing it to ready-to-build status. flag The company now focuses on final engineering, interconnection planning, and commercial negotiations. flag Revolve plans to evaluate registering its 400 MW Presa Nueva Wind Project in a 2026 qualification window under Mexico’s broader initiative to add 5,970 MW of private wind and solar capacity by 2030.