flag A Ghana tribunal ordered Justmoh to pay APSL $33.3M plus interest, while APSL owed Justmoh $7.1M for port project work.

flag A Ghana Arbitration Centre tribunal has ruled that Justmoh Construction must pay Ashanti Port Services $33.3 million plus 4% interest for unpaid mobilisation fees on the Boankra Inland Port project, while APSL must pay Justmoh $7.1 million for completed earthworks. flag The tribunal found Justmoh lawfully terminated the contract despite the work not being explicitly covered in the agreement, citing strong documentation and consultant validation. flag Justmoh will cover 75% of APSL’s legal and arbitration costs. flag The dispute, initiated in December 2023, concluded in December 2025 with the award. flag APSL’s CEO praised the outcome as fair and a boost to Ghana’s dispute resolution system.