Orezone Gold Corp. achieved its first gold pour at its expanded Bomboré Mine in Burkina Faso on December 15, 2025.
Orezone Gold Corporation achieved its first gold pour on December 15, 2025, from the expanded 2.5 million tonnes per annum hard rock processing plant at its Bomboré Gold Mine in Burkina Faso.
The facility, completed on time and on budget, reached 78% of its designed capacity in early operation.
Commercial production is expected to start in early 2026, increasing annual gold output by 45% to 170,000–185,000 ounces.
The company is advancing a second phase that could raise production to 220,000–250,000 ounces annually.