NDPHC restored 450MW to Nigeria’s grid after maintenance, boosting power supply and supporting national energy goals.
NDPHC restored 450MW to Nigeria’s grid after maintenance at the Geregu plant, part of broader efforts to revive dormant power assets, including six recovered gas turbines adding 875MW.
The 225MW Gbarain plant in Bayelsa was also restored, and a 7.5MVA substation project began in Abia State under the National Integrated Power Project, with a second substation planned for 2026.
The company reported financial recoveries, operational reforms, and progress on solar and transmission projects, supporting Nigeria’s push for reliable electricity and economic growth.
3 Articles
NDPHC restauró 450 MW a la red de Nigeria después del mantenimiento, impulsando el suministro de energía y apoyando los objetivos energéticos nacionales.