flag Rogers' 5G rollout in Toronto subways is delayed to mid-2027 due to asbestos, limited work hours, and maintenance priorities.

flag A new TTC report reveals delays in Rogers' 5G rollout across Toronto’s subway system due to asbestos cleanup, limited construction windows, and prioritized maintenance work. flag The project, which aims to deliver 80% coverage by December 2025 and full service by December 2026, now projects only 70% completion by year-end and 88% by end of 2026, with full completion expected by mid-2027. flag Work remains restricted to overnight and weekend hours, and canceled subway closures have slowed progress. flag Service is active in major downtown tunnels and parts of Lines 1 and 2, but no work has started on Line 4. flag The federal government set the original timeline as part of spectrum licensing conditions.