flag A second fire at Novelis’ Oswego plant on Nov. 20, 2025, caused evacuations and disrupted Ford’s F-150 production, just months after a prior blaze.

flag A second major fire at Novelis’ Oswego, New York aluminum plant on November 20, 2025, prompted evacuations and a four-alarm response, just two months after a similar incident disrupted production. flag The plant, a key supplier for Ford’s F-150 trucks, had already seen output cut due to the September fire, leading Ford to pause F-150 Lightning production and reduce its profit forecast by up to $2 billion. flag Though Ford expects to recover about $1 billion in 2026 by shifting production, the latest fire’s impact on Novelis’ accelerated December restart plan remains unclear. flag No injuries were reported, and crews are on site to ensure the fire is fully extinguished.