The Scottish Government will decide on a 191km power line project, with Highland Council commenting but not deciding.
Highland Council is a consultee, not the decision-maker, in the proposed 191km Spittal to Beauly 400kV power line project, which aims to boost Scotland’s renewable energy network and deliver £35 million in community benefits.
The Scottish Government’s Energy Consents Unit will decide on the project, facing opposition over visual impact and threats to 28 scheduled monuments.
The council will submit its formal response by November 7, 2025, after a joint committee review, with no public hearings.
SSEN Transmission is assessing alternative routes and tower placements, and the public can engage via the ECU portal using reference ECU00006008.
Construction could begin in 2025.
El Gobierno escocés decidirá sobre un proyecto de línea eléctrica de 191 km, con el Consejo de Highland comentando pero no decidiendo.