flag A $19 million grid upgrade in northern Ohio, nearing completion, is enhancing power reliability for nearly 10,000 residents by replacing aging infrastructure with storm-resistant components.

flag A $19 million grid upgrade by FirstEnergy is nearing completion in northern Trumbull and parts of Ashtabula counties, improving electrical reliability for nearly 10,000 residents and businesses. flag The project replaced aging infrastructure with stronger poles, thicker wires, and deep concrete foundations to better withstand storms and accidents. flag Part of a larger $28 billion modernization effort through 2029, the work aims to reduce outages and speed up power restoration. flag The upgraded transmission line is expected to energize later in October 2025.