flag A £5.9M railway bridge in Scotland nears completion, with a rail closure planned Dec. 24–Jan. 2 for its installation.

flag A £5.9 million railway bridge is nearing completion at the former Exxon site in Bowling, Scotland, as part of the Glasgow City Region Deal. flag The structure, now fully cast with 1,860 tonnes of concrete, is on schedule after summer construction began. flag The next major step, moving the 300-tonne bridge into place, will require a three-week rail closure from December 24 to January 2, affecting services between Dalmuir and Balloch/Helensburgh Central, and Glasgow Queen Street and Crianlarich, including Caledonian Sleeper routes. flag Passengers are advised to check for updates via Network Rail’s website or social media.