Flexjet sues Honeywell over failed engine maintenance, citing pre-pandemic delays and defective parts, seeking up to $1.1 billion in damages.
Flexjet has sued Honeywell over alleged failures to meet engine maintenance obligations under a 2018 agreement, citing persistent delays due to parts shortages—particularly defective bearings—and staffing issues that predated the pandemic.
Despite paying $30,000 daily in liquidated damages through 2021, Flexjet claims Honeywell’s performance was consistently inadequate.
In 2021, Honeywell invoked force majeure over pandemic disruptions, but Flexjet argues the delays were systemic and preexisting.
The New York Supreme Court granted summary judgment to Flexjet on key points, and Honeywell is appealing; the case could result in damages up to $1.1 billion.
Flexjet demanda a Honeywell por el mantenimiento fallido del motor, citando retrasos previos a la pandemia y piezas defectuosas, buscando hasta $1.1 mil millones en daños.