flag Nagaland's MP warns of highway delays due to monsoon damage and technical issues, with key sections expected by late 2025 or 2026.

flag Nagaland’s Lok Sabha MP S. Supongmeren Jamir raised concerns over recurring disruptions on the Dimapur-Kohima four-lane highway, particularly near New Chümoukedima, during a review meeting on October 11, 2025. flag He urged NHIDCL to provide timely updates on delays affecting the project and related roads, citing public inconvenience. flag NHIDCL attributed setbacks to monsoon damage, technical issues, and local challenges. flag While the Dimapur bypass and Package 2 are complete, Package 3 is expected by December 2025, and Package 1 awaits landslide protection approval. flag The Kohima bypass faces delays due to tunnel issues, and the Kohima–Jessami road is on track for completion by September 2026. flag A follow-up meeting is planned for November.