flag A tribunal ordered a developer to pay interest, deliver amenities, and transfer common areas within two months after rejecting flawed completion claims.

flag The Odisha Real Estate Appellate Tribunal ruled in favor of homebuyer Surya Prakash, upholding ORERA’s decision against a developer in Andharua. flag The tribunal rejected the builder’s claim that the project was exempt from RERA, citing invalid completion certificates and BDA’s rejection of the occupancy application due to construction flaws and missing documents. flag It ordered the developer to pay 10.2% interest on Rs 47.84 lakh for delayed possession, deliver promised amenities, obtain a valid occupancy certificate, form an allottees’ association, and transfer common areas within two months, with further legal action if unmet.