Hydro One seeks public input on a draft study for a 500-kV transmission line to meet Southwestern Ontario’s rising power needs by 2035.
Hydro One is seeking public feedback on a draft environmental study for its proposed Longwood to Lakeshore transmission line project, aimed at meeting Southwestern Ontario’s projected quadrupling of electricity demand by 2035.
The project involves building two 500-kilovolt lines, with the first line expected to be operational by 2030 and capable of powering a city like London, Ontario.
The preferred route, spanning 120 kilometers with nearly 30 kilometers using existing corridors, aims to reduce environmental and community impacts.
Public comments are due by October 15, 2025, though engagement will continue.
The final environmental study is expected by early 2026, with construction projected to begin in 2027.
Reports are available online and at select libraries.