flag The Silver Lake Project in Rochester, Minnesota, delayed nearly a year due to permitting issues, now set for September 2023 with revised costs of $15.1 million.

flag The $15 million Silver Lake Project in Rochester, Minnesota, has been delayed nearly a year due to state and federal permitting delays, pushing the start date to September 2023. flag The project, which includes dam modifications and sediment removal, had its construction bids canceled. flag Delays stem from the Minnesota DNR needing more time to review the design of a new recreational wave pool and the U.S. Army Corps of Engineers facing staffing shortages. flag Despite the delay, the city says the revised timeline will meet all deadlines and will not affect the dam’s operation or flood control system. flag Updated cost estimates now place the project at about $15.1 million.