Lansdowne House boundary wall project faced delays and cost disputes between OPW and ESB.
The Office of Public Works faced delays and extra costs in a €490,000 boundary wall project at Lansdowne House in Dublin.
The ESB initially tried to charge an additional €57,000 to divert an electrical cable, pushing the completion date from December 2022 to December 2024.
The OPW refused the fee and hired an external contractor.
Both the OPW and ESB declined to comment.