2026 Gardiner Expressway rehabilitation completion, four months ahead due to $73m for 24/7 construction.

Toronto's Gardiner Expressway rehabilitation is four months ahead of schedule, Mayor Olivia Chow announced. Initially set for completion in April 2027, the project is now expected to finish by April 2026, thanks to a $73 million funding boost for 24/7 construction. This $300 million effort is part of a broader multi-billion-dollar revamp of the aging highway, which serves around 140,000 daily users, aiming to alleviate traffic congestion.

October 10, 2024
6 Articles