South Star Battery Metals completes Santa Cruz Phase 1 graphite mine in Brazil, 50,000 tonnes of ore placed, commissioning in 6-7 weeks.

South Star Battery Metals Corp. announces substantial completion of its Santa Cruz Phase 1 graphite mine in Brazil. Mine preparations and key infrastructure are complete, with 50,000 tonnes of ore placed on the ore pad by August end. Commissioning of plant areas, power distribution, and support services is underway, with mainline powerline completion scheduled for final grid connection. Commissioning is expected in 6-7 weeks.

July 29, 2024
3 Articles

Further Reading