Toshiba ESS receives order for steam turbines and generators to upgrade Kenya's Olkaria I geothermal plant, increasing its output to 63MW.

Toshiba Energy Systems & Solutions Corporation (Toshiba ESS) has received an order to supply steam turbines and generators for the renovation of Units 1 through 3 at Kenya's oldest geothermal power plant, Olkaria I, increasing its output from 45MW to 63MW. The order was received from SEPCOIII Electric Power Construction Co. Ltd., the chosen Engineering, Procurement, and Construction contractor for the project. The renovation aligns with Kenya's Vision 2030, aiming for a 100% green energy transition by 2030.