Kaduna Electric plans to invest N350m to upgrade Millennium City Injection substation, benefiting 20,000 customers.
Kaduna Electric plans to invest N350m to upgrade its Millennium City Injection substation, addressing power demand for over 20,000 customers in seven communities. The project involves procuring a 7.5MVA transformer, constructing a new 11KV feeder, and increasing substation capacity to 2x7.5MVA. The company's COO, Abubakar Sadiq Mohammed, appeals to customers to pay their bills to support the initiative.
March 16, 2024